Downtown Franklinton sidewalk construction (Segment A2)
Washington Parish
Summary
The parish took the low bid — about $148,000 under the engineer's estimate — to build sidewalk segments D and E along LA 16.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 28, 2026.
Impact analysis
$837,404.15 state project cost, about $148,000 under the estimate.
Pedestrians along the LA 16 corridor get safer sidewalks.
Mentions & discussions (3)
Parish Council - Sep 28, 2026
The parish took the low bid — about $148,000 under the engineer's estimate — to build sidewalk segments D and E along LA 16.
Parish Council - May 18, 2026
The parish is moving forward on a grant-funded sidewalk project along Main Street, wrapping the junior high and extending down Bean Street — parish pays 10% of construction plus all engineering, capped at $218,497.
Parish Council - Jan 12, 2026
The state-funded downtown Franklinton sidewalk segment from around Ellis Street to the fairgrounds is finished and formally closed out with DOTD.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Washington Parish
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.